In a few years, CMAA Construction-Manager certification exam has become a very influential exam which can test computer skills.The certification of CMAA certified engineers can help you to find a better job, so that you can easily become the IT white-collar worker,and get fat salary.
However, how can pass the CMAA Construction-Manager certification exam simple and smoothly? ITCertMaster can help you solve this problem at any time.
ITCertMaster is a site which providing materials of International IT Certification. ITCertMaster can provide you with the best and latest exam resources.The training questions of CMAA certification provided by ITCertMaster are studied by the experienced IT experts who based on past exams. The hit rate of the questions is reached 99.9%, so it can help you pass the exam absolutely. Select ITCertMaster, then you can prepare for your CMAA Construction-Manager exam at ease.
Our materials of CMAA Construction-Manager international certification exam is the latest collection of exams' questions, it is covering a comprehensive knowledge points. It is the best assistant for you preparation about the exam. You just need to spend 20-30 hours to remember the content of the questions we provided.
All customers that purchased the materials of CMAA Construction-Manager exam will receive the service that one year's free update, which can ensure that the materials you have is always up to date. If you do not pass the exam after using our materials, you can provide the scanning items of report card which provided by authorized test centers (Prometric or VUE) . we will refund the cost of the material you purchased after verified, We guarantee you interests absolutely.
Before you select ITCertMaster, you can try the free download that we provide you with some of the exam questions and answers about CMAA Construction-Manager certification exam. In this way, you can know the reliability of ITCertMaster.
ITCertMaster is the best choice which can help you to pass the CMAA certification exams, it will be the best guarantee for your exam.
No matter what level of entry you are for your CMAA Certification, you will pass your Construction-Manager exam, FAST!
Quickly select ITCertMaster please! Select ITCertMaster is equivalent to choose a success. With it you can complete your dreams quickly!
Easy and convenient way to buy: Just two steps to complete your purchase, we will send the product to your mailbox quickly, you only need to download e-mail attachments to get your products.
CMAA Construction-Manager Exam Syllabus Topics:
| Section | Objectives |
|---|---|
| Project Controls and Risk Management | - Project performance monitoring - Risk identification and mitigation |
| Quality and Safety Management | - Construction safety programs and compliance - Quality assurance and quality control |
| Project Management Fundamentals | - Scope, schedule, and budget management - Project planning and delivery methods |
| Cost and Financial Management | - Cash flow and financial reporting - Cost estimating and control |
| Contract Administration | - Construction contracts and procurement - Change orders and claims management |
| Project Closeout and Commissioning | - Commissioning and handover - Closeout procedures and documentation |
| Schedule Management | - Schedule development and tracking - Critical path method (CPM) |
CMAA Certified Construction Manager (CCM) Sample Questions:
Question #1
When the CM assists the owner in prequalifying, evaluating, or screening potential contractors, especially as it relates to safety programs, the CM should evaluate the contractor's lost time frequency rate; lost time severity average; OSHA 200; OSHA 300; experience modification rate; and an up-to-date list of any OSHA citations issued to them in the last three years, including the disposition of each citation. This is important because:
A. a contractor with a poor safety record may increase the owner's risk and worker compensation costs.
B. extensive documentation is required to demonstrate sufficient due diligence.
C. contractors only monitor safety if they understand the owner's emphasis on safety.
D. a contractor with a poor safety record is likely to be a low bidder.
Question #2
The general contractor on a $1.2 billion terminal at an airport finds out that, due to supply chain issues, there is a 60% risk that they will not be able to get steel onsite for 10 weeks. The late start date of steel installation is four weeks away. Such a delay would cost the owner $75,000 per week to recover. What is the expected monetary value of risk?
A. $1.2 million
B. $2.7 million
C. $450,000
D. $270,000
Question #3
Which of the following addresses the administrative and reporting requirements for a Construction Manager during execution of a project?
A. Construction Administration Guidelines
B. Standards of Practice
C. Project Administration Guidelines
D. Contract Administration Guidelines
Question #4
Program management includes the early participation of the program manager in developing and making which of the following types of decisions that become the basis of a capital improvement program?
A. Safety
B. Jurisdictional
C. Staffing
D. Business
Question #5
The chief estimator for a construction company is asked to provide an estimate based on known project characteristics, such as square footage and unit prices. The estimator will MOST likely be employing which technique?
A. Bottom Up Estimating
B. Parametric Estimating
C. Conceptual Estimating
D. Analogous Estimating
Solutions:
| Question #1 Correct Answer: A | Question #2 Correct Answer: B | Question #3 Correct Answer: D | Question #4 Correct Answer: D | Question #5 Correct Answer: B |